PROJECT CASSANDRA · ARG-BLC1 DIAGNOSTIC HANDOVER BRIEF

Possible cause of the fault: Compressor C2 internal bypass

Demo Cooling Plant A · Chiller CH-1 (Twin-Stage Water-Cooled Chiller · 350 kW)

REPORT ID: CAS-CH1-2023-1019
ONSET DATE: Oct 16, 2023
ALARM TRIGGERED: Oct 19, 2023 (Day 3)
ADVISORY TIER: Medium (76.4% · 15% Reserve)
Alarm Triggered (Oct 19): Predicted vs. Real EER do not match (−8.2%)
Isolated 105 days before mechanical breakdown while leaving chilled water temperature held 7.0°C setpoint.
Avoidable Loss: +8,839 kWh (£2,121)

Thermodynamic & Twin-Stage Evidence

Healthy Twin Control (C1) −0.06 EER (0.0% drift)
Faulted Target Stage (C2) −0.64 EER (+3.81 kW)
Low-Load Suction / Discharge P_ev +51 mbar / P_cd −24 mbar
Digital Twin Blind RMSE 1.62 kW (6,531 OOS hrs)

Ruled-Out Causes & Sensor Honesty

Condenser Fouling 0.0% (High-load penalty absent)
Refrigerant Undercharge 0.0% (C1 subcooling normal)
Water Temperature Sensor Drift 0.0% (Shared C1/C2 probes)
Unmeasured Sensor Reserve 15.0% (No discharge gas sensor)

Recommended 15-Minute On-Site Technician Verification Plan

01
Clamp-On Discharge Gas Temperature Check (5 mins): Compare Compressor C2 discharge pipe temperature against C1 at 100–200 kW part load. Elevated C2 discharge superheat confirms hot-gas internal recirculation across the unloader valve.
02
Unloader Solenoid & Slide/Port Seating Inspection (5 mins): Energise and de-energise the C2 capacity unloader coil while monitoring suction pressure drop to verify complete mechanical seating after the Oct 15–16 34-hour idle stop.
03
Lead/Lag Staging Swap Mitigation (5 mins): Prioritize healthy Compressor C1 as lead stage at part load (<220 kW) until the C2 unloader valve seal is serviced, recovering ~£590/month in avoidable electricity.
Generated by Project Cassandra ARG-BLC1 · Industrial Thermal Diagnostics projectcassandra.uk · contact@projectcassandra.uk